WP2 D8 EuRRECa Newsletter – month 12 31/01/2019
WP2 D13 Data Access Policy – draft 31/01/2019
WP3 D16 Tool for checking the quality of registries 31/01/2019
WP3 D17 Interim Report on Quality Assurance & Evaluation – Month 12 31/01/2019
WP4 D22 Generic PRO tool for inclusion in Core Endocrine Registry 31/01/2019
WP5 D25 Report on the needs of patients in registries 31/01/2019
WP6 D31 Beta version of Core Endocrine Registry 31/01/2019
WP1 D1 IAB progress report – month 13 28/02/2019
WP2 D9 EuRRECa Newsletter – month 18 31/07/2019
WP3 D18 Interim Report on Quality Assurance & Evaluation – Month 18 31/07/2019
WP5 D26 Report on existing registries 31/07/2019
WP6 D32 Fully operating version of Core Endocrine Registry 31/07/2019
WP2 D14 Data Access Policy – final 30/09/2019

MILESTONES

WP1 45 IAB meeting – month 12 01/02/2019
WP1 2 Project Governing Board Meeting at Endo ERN – Month 12 01/02/2019
WP1 7 EuRRECa Project Group Meeting at Endo-ERN – Month 12 01/02/2019
WP2 14 Exhibition and presentation at Endo-ERN general assembly 2019 01/02/2019
WP3 20 Presentation at Endo-ERN general assembly and EuRRECa annual meeting 2019 01/02/2019
WP4 29 Presentation at EuRRECa Project Group Meeting to coincide with Endo-ERN – month 12 01/02/2019
WP5 33 Presentation at the EuRRECa Project Group Meeting to coincide with Endo-ERN general assembly – month 12 01/02/2019
WP2 12 Exhibition and presentation at ESE 2019 01/06/2019
WP5 37 WP05 meeting, workflow for appraisal of registries becomes operational 01/06/2019
WP1 5 PGB Meeting – Month 18 01/08/2019
WP4 26 WP04 Board Meetings together with chair of the Endo-ERN – month 18 01/08/2019
WP6 41 Launch of the Core Endocrine Registry with PROs 01/09/2019 imminent
WP2 18 Exhibition and presentation at ESPE 2019 01/10/2019 next week
WP5 38 WP05 meeting, launch of the appraisal report for the Core Endocrine Registry 01/11/2019